All projects

Abnormal load route in Lozère: 123 structures assessed

Itinéraire de convois exceptionnels en Lozère : 123 ouvrages diagnostiqués

Survey, inspection, reassessment and monitoring of 93 walls, 29 bridges and a gallery for 157 t convoys to the Pied-de-Borne power station.

To replace a transformer at the Pied-de-Borne hydroelectric power station, abnormal loads had to use departmental roads RD51 and RD901. EDF commissioned THEOREMS to survey, assess and recalculate all the structures along the route for convoys of up to 157.25 t gross weight.

The study covered 93 retaining walls, 29 standard bridges and an underground gallery. The structures were then monitored before, during and after the convoys crossed.

Characteristics

  • Structures assessed: 93 retaining walls, 29 bridges, 1 gallery
  • Convoy: 157.25 t gross weight

Services provided

  • Survey and mapping of the structures
  • Detailed inspection by drone and under-bridge unit
  • Reassessment of all the structures
  • Diagnosis of the arch at Villefort with a full 3D scan
  • Saugnac gauges to monitor cracks
  • Brass markers and wall displacement surveys before, during and after the crossing
  • Drone monitoring during the convoy crossing

Photos

  • Abnormal load route in Lozère: 123 structures assessed – view 1
  • Abnormal load route in Lozère: 123 structures assessed – view 2
  • Abnormal load route in Lozère: 123 structures assessed – view 3

Similar projects