Assessment campaign on 17 bridges, often steel and a century old: weight restrictions proposed and urgent works identified.
Under a framework contract, THEOREMS checked the load capacity of seventeen bridges of the Aisne Departmental Council, most of them built between 1921 and 1949. Each study leads to an operational conclusion: weight restriction, urgent works or further investigations.
Structures assessed
| Structure | Built | IQOA rating | Existing restriction | Conclusion |
|---|---|---|---|---|
| D0129 – Seraucourt-le-Grand | 1929 | 3U | 19 t | Restriction to 12 t |
| D0131 – Saint-Simon | 1941 | 3U | 40 t | Restriction to 30 t |
| D0182 – Marle | ? | 3U | – | No restriction, urgent works |
| D0231 – Neuvillette | ? | 3 | – | No restriction, urgent works |
| D249A – Iron | 1923 | 3U | 15 t | Restriction to 19 t |
| D0394 – Lesquielles-Saint-Germain | 1922 | 3U | – | No restriction, urgent works |
| D0480 – Neufchâtel | 1949 | 3 | – | 19 t pending works, then no restriction |
| D0493 – Bourg-et-Comin | 1948 | – | – | 19 t pending works, then no restriction |
| D0510 – Fontaine-les-Clercs | 1922 | 3U | 19 t | Restriction to 19 t |
| D0390 – Omissy | 1925 | 3U | – | Restriction to 12 t |
| D110D – Pinon | 1949 | 3S | – | 19 t on 2 lanes or 26 t on 1 lane |
| D0095 – Tavaux-et-Pontséricourt | 1922 ? | 2E | – | 19 t pending works, then no restriction |
| D0459 – Marle | after 1940 | 2E | – | 25 t pending works, then no restriction |
| D0460 – Marle | ? | 1 | – | No restriction if arch > 45 cm; investigations required |
| D0473E | 1971 | 2E | – | No restriction |
| D0623 – Origny-Sainte-Benoîte | 1921 | – | – | Restriction to 19 t |
| D0623A | 1921 | 2 | – | Restriction to 19 t |