All projects

Reconstruction of the Rametz bridge over the Hogneau

Reconstruction du pont du Rametz sur l’Hogneau

Brick arch replaced by a reinforced concrete arch, restoring the ecological continuity of the Hogneau.

OA 5237 carries the RD942 over the Hogneau at Bavay. This brick masonry arch bridge no longer offered a safe crossing. The Nord Departmental Council decided to rebuild it, with architectural changes and measures to restore the ecological continuity of the watercourse.

THEOREMS provided full design and project management for the new reinforced concrete arch, up to the load tests.

Characteristics

  • Existing structure: brick masonry arch
  • New structure: reinforced concrete arch

Services provided

  • Condition survey, reassessments and investigations (geotechnical boreholes, coring, bathymetry, topography)
  • Studies to restore ecological continuity, with hydraulic modelling
  • Water Act application
  • DIA, AVP, PRO, ACT, VISA, OPC, DET and AOR assignments
  • Load tests

Photos

  • Reconstruction of the Rametz bridge over the Hogneau – view 1
  • Reconstruction of the Rametz bridge over the Hogneau – view 2
  • Reconstruction of the Rametz bridge over the Hogneau – view 3
  • Reconstruction of the Rametz bridge over the Hogneau – view 4
  • Reconstruction of the Rametz bridge over the Hogneau – view 5

Similar projects